Dairy Digester

Project Overview

GLIC was brought in to provide ground up electrical fabrication for a renewable gas facility on a dairy farm, which included the installation of power distribution, process control, commissioning, and start-up support. The goal of the project was to extract methane from the manure, which was then converted into renewable natural gas for use in the community.

 

To complete the project, GLIC coordinated multi-trade scheduling for the duration of the installation, working closely with other contractors to ensure timely completion. The GLIC team also provided ongoing support throughout the project, working closely with the client to ensure that all electrical systems were properly installed and fully functional.

 

Thanks to the expertise and attention to detail of the GLIC team, the project was completed on time and within budget, providing the community with a reliable and sustainable source of natural gas.